CAT 2001 — DILR Question 13
Answer the following question based on the information given below.
Figure 1 shows the amount of work distribution, in man-hours, for a software between offshore and onsite activities. Figure 2 shows the estimated and actual work effort involved in the different offshore activities in the same company during the same period. [Note: Onsite refers to work performed at the customer's premise and offshore refers to work performed at the developer's premise.]

If 50 percent of the offshore work were to be carried out onsite, with the distribution of effort between the tasks remaining the same, the proportion of testing carried out offshore would be
Answer & solution
Correct answer: 30 percent
- A
40 percent
30 percent
- C
50 percent
- D
70 percent
Man-hours required for testing offshore = 290
50% of this is now carried out onsite.
∴ Man-hours for testing offshore = 290 − 145 = 145
And man-hours for testing onsite = 150 + 145 = 295
Total man-hours of testing = 145 + 295 = 440
∴ Required percentage = (145 × 100)/440 ≈ 33%
Hence, option (b).
Related Pie-Charts questions
- Which of the work requires as many man-hours as that spent in coding?…
- Roughly what percentage of the total work is carried out onsite?…
- The total effort in man-hours spent onsite is nearest to which of the following?…
- If the total working hours were 100, which of the following tasks will account f…
- If 50 percent of the offshore work were to be carried out onsite, with the distr…
- The cost in rupees per ton of oil moved by rail and road happens to be roughly…