CAT 2017 Slot 1 — QA Question 2
Man Days (single group of people)Easy
A person can complete a job in 120 days. He works alone on Day 1. On Day 2, he is joined by another person who also can complete the job in exactly 120 days. On Day 3, they are joined by another person of equal efficiency. Like this, everyday a new person with the same efficiency joins the work. How many days are required to complete the job?
Answer & solution
Correct answer: 15
Answer: 15
Solution
Easy
Everyone has the same rate per day. With workers on day , the work done on day is . Sum the days until the total work equals — that turns into the sum .
1
Work done each day. On day there are people, each doing of the job.
2
Total work over days equals . Add days through .
3
Solve for . Need .