Amal can complete a job in 10 days and Bimal can complete it in 8 days. Amal, Bimal and Kamal together complete the job in 4 days and are paid a total amount of Rs 1000 as remuneration. If this amount is shared by them in proportion to their work, then Kamal’s share, in rupees, is
Answer & solution
100
- B
200
- C
300
- D
400
Solution
In one day, Amal, Bimal and Kamal complete of the work.
In one day, Amal and Bimal complete of the work.
So amount of work done by Kamal alone in one day is = of the work
∴ Fraction of work done by Kamal in 4 days = 4 × =
⇒ Amount received by Kamal will be 1/10th of total amount = 1/10 × 1000 = Rs. 100
Hence, option (a).