CAT 2020 Slot 3 — QA Question 5
A contractor agreed to construct a 6 km road in 200 days. He employed 140 persons for the work. After 60 days, he realized that only 1.5 km road has been completed. How many additional people would he need to employ in order to finish the work exactly on time?
Answer & solution
Correct answer: 40
Answer: 40
Easy
Find the work rate from the first phase, scale it to the remaining work and remaining days, and use the proportion (men days) constant for a fixed amount of work.
Work done so far. In days, km of km is built.
Days the original crew would still need. The men did of the work in days, so the whole job at that pace takes days; the remaining would take the same crew more days.
Days actually available.
Apply men days constant. The same remaining work: men over days equals men over days.