CAT 2021 Slot 3 — QA Question 4
One day, Rahul started a work at 9 AM and Gautam joined him two hours later. They then worked together and completed the work at 5 PM the same day. If both had started at 9 AM and worked together, the work would have been completed 30 minutes earlier. Working alone, the time Rahul would have taken, in hours, to complete the work is:
Answer & solution
10
- B
12
- C
12.5
- D
11.5
Easy
Compare two scenarios that finish the same job. In the real scenario Rahul works longer than Gautam; in the hypothetical both start together and finish min sooner. Equating the total work in the two scenarios gives the ratio of their rates, which then yields Rahul's solo time.
Set up the two scenarios. Let Rahul's rate be and Gautam's rate be (units/hour). Actual: Rahul is h, Gautam joins at so works h. Hypothetical: both work together and finish min earlier, i.e. by , which is h each.
Equate the work and find the rate ratio. Both scenarios complete the identical job, so (1)(2).
Total work, then Rahul's solo time. Substitute into the actual work, then divide total work by Rahul's rate.