CAT 2022 Slot 3 — QA Question 3
Man Days (single group of people)Easy
A group of N people worked on a project. They finished 35% of the project by working 7 hours a day for 10 days. Thereafter, 10 people left the group and the remaining people finished the rest of the project in 14 days by working 10 hours a day. Then the value of N is
Answer & solution
- A
23
140
- C
36
- D
150
Solution
Easy
Work = (people)(days)(hours)(efficiency). Set up the proportion: the first stretch did with people, the second did the remaining with people. Equate "work per unit fraction" and solve for .
1
Write total man-hours for each phase (efficiency cancels later):
2
Man-hours are proportional to work done, so:
3
Simplify. Divide both sides by and clear the decimals ():