CAT 2024 Slot 2 — QA Question 21
Amal and Vimal together can complete a task in 150 days, while Vimal and Sunil together can complete the same task in 100 days. Amal starts working on the task and works for 75 days, then Vimal takes over and works for 135 days. Finally, Sunil takes over and completes the remaining task in 45 days. If Amal had started the task alone and worked on all days, Vimal had worked on every second day, and Sunil had worked on every third day, then the number of days required to complete the task would have been
Answer & solution
Answer: 139
Hard
First find the three individual one-day work rates from the two pair-rates and the actual 75/135/45-day completion. Then simulate the new schedule (Amal daily, Vimal every 2nd day, Sunil every 3rd day) and find the day the work hits 1.
Pair rates. Let be daily fractions done by Amal, Vimal, Sunil.
Use the actual completion. . Substitute and .
Recover all three rates.
Simulate the new schedule. In days Amal works all days, Vimal days, Sunil days. Work done . Ignoring floors gives , i.e. , so test .