Man Days (single group of people)CAT Previous-Year Questions

8 previous-year questions on Man Days (single group of people) from CAT, with full solutions. Practise free — check answers as you go; sign in to save your progress.

Back
8 questions

Man Days (single group of people) · CAT PYQs

CAT 2024 Slot 1 · QA
Q1.

Renu would take 15 days working 4 hours per day to complete a certain task whereas Seema would take 8 days working 5 hours per day to complete the same task. They decide to work together to  complete this task. Seema agrees to work for double the number of hours per day as Renu, while Renu agrees to work for double the number of days as Seema. If Renu works 2 hours per day, then the number of days Seema will work, is

CAT 2022 Slot 3 · QA
Q2.

A group of N people worked on a project. They finished 35% of the project by working 7 hours a day for 10 days. Thereafter, 10 people left the group and the remaining people finished the rest of the project in 14 days by working 10 hours a day. Then the value of N is

CAT 2020 Slot 3 · QA
Q3.

A contractor agreed to construct a 6 km road in 200 days. He employed 140 persons for the work. After 60 days, he realized that only 1.5 km road has been completed. How many additional people would he need to employ in order to finish the work exactly on time?

CAT 2017 Slot 1 · QA
Q4.

A person can complete a job in 120 days. He works alone on Day 1. On Day 2, he is joined by another person who also can complete the job in exactly 120 days. On Day 3, they are joined by another person of equal efficiency. Like this, everyday a new person with the same efficiency joins the work. How many days are required to complete the job?

CAT 2002 · QA
Q5.

It takes 6 technicians a total of 10 hours to build a new server from Direct Computer, with each working at the same rate. If six technicians start to build the server at 11 a.m. and one technician per hour is added beginning at 5 p.m., at what time will the server be complete?

CAT 1995 · QA
Q6.

A group of men decided to do a job in 8 days. But since 10 men dropped out every day, the job got completed at the end of the 12th day. How many men were there at the beginning?

CAT 1993 · QA
Q7.

A group of workers was put on a job. From the second day onwards, one worker was withdrawn each day. The job was finished when the last worker was withdrawn. Had no worker been withdrawn at any stage, the group would have finished the job in two-third the time. How many workers were there in the group?

CAT 1991 · QA
Q8.

Alord got an order from a garment manufacturer for 480 Denim Shirts. He brought 12 sewing machines and appointed some expert tailors to do the job. However, many didn’t report to duty. As a result, each of those who did, had to stitch 32 more shirts than originally planned by Alord, with equal distribution of work. How many tailors had been appointed earlier and how many had not reported for work?