CAT 1996 — DILR Question 16
Direction: Answer the questions based on the following information.
Mulayam Software Co., before selling a package to its clients, follows the given schedule.
âââââââ
âââââââThe number of people employed in each month is:
âââââââ
âââââââ
Due to overrun in ‘design’, the design stage took 3 months, i.e. months 3, 4 and 5. The number of people working on design in the fifth month was 5. Calculate the percentage change in the cost incurred in the fifth month. (Due to improvement in ‘coding’ technique, this stage was completed in months 6-8 only.)
Answer & solution
Correct answer: 150%
- A
225%
150%
- C
275%
- D
240%
Originally for the fifth month, 4 people were scheduled to do coding. This would have cost them (10000 × 4)
= Rs. 40,000. Now there are 5 people who are working on design in the fifth month.
The total cost for this would be (20000 × 5) = Rs.1,00,000.
Hence, percentage change in the cost incurred in the fifth month = 100 = 150%
Related Tables questions
- What is the percentage increase in investment of B, C, D and E from year 1 to ye…
- What is the ratio of investments of E to F for the years 1 to 3?…
- What is D’s contribution as a percentage of total investments in year 2?…
- For which company is investment not increased from year 1 to year 3?…
- What is the percentage difference in investments of companies A, B, C and compan…
- The average revenue collected in the given 7 years is approximately…