CAT 1996DILR Question 18

TablesEasy
Passage / Data

Direction: Answer the questions based on the following information.

Mulayam Software Co., before selling a package to its clients, follows the given schedule.

​​​​​​​

​​​​​​​The number of people employed in each month is:

​​​​​​​​​​​​​​

What is the difference in cost between the old and the new techniques?

Answer & solution

  • A

    Rs. 30,000

  • Rs. 60,000

  • C

    Rs. 70,000

  • D

    Rs. 40,000

Solution

The difference in the cost will arise only because of the following months: 5, 6 and 8. And we can compare the costs as given below

​​​​​​​

​​​​​​​It can be clearly seen that the difference in the cost between the old and the new technique is Rs. 60,000.